Electricity Act, 2003–Sec. 125–Limitation Act, 1963–Sec. 5–Delay of 161 days in filing the appeal before Supreme Court–Condonation–Though the delay was occurred for prosecuting the review petition, yet it was also delayed for 37 days–Merely because the Tribunal condoned the delay in filing
the review petition, it cannot be held that there was due diligence–Lack of good faith on part of appellant in conducting his case–Declined to condone the delay.
Suryachakra Power Corporation Ltd. (M/s.) vs. Electricity Department & Ors. – (SC)